Case Study: KMI, School Lane, Preston 32 UID scheme/strong>
✔ Spring 2012
✔ Value: £100K
Scheme
To demolish an existing CSO chamber and construct a new chamber complete with screens and telemetry, works were undertaken on behalf of KMI.
Scope of works
This site was at the end of a narrow lane adjacent to a school as well as a footpath and allotments, our primary objective was to maintain all access and work with our neighbours
Through all phases of the job.
We had to demolish the existing CSO, yet maintain flows, overpumping was required.
The new CSO was a RC structure, shuttering, rebar and concreting was all undertaken by JMK.
Scheme was finished on programme and flows turned through new chamber.